Project schedule updated through Dec. 13

The Thursday, Dec. 5, closure of US 60 between Superior and Miami for the Pinto Creek Bridge project has been canceled. Instead, motorists should expect flaggers near the work zone between 6:30 a.m. and 4:30 p.m.

The work schedule for the week of Dec. 9, is as follows:

Monday, Dec. 9 - Lane restrictions and flaggers between 6:30 a.m. and 4:30 p.m.
Tuesday, Dec. 10 - Full closure between 9 a.m. and 1 p.m. Lane restrictions and flaggers, if needed, between 1 p.m. and 4:30 p.m.
Wednesday, Dec. 11 - Lane restrictions and flaggers between 6:30 a.m. and 4:30 p.m.
Thursday, Dec. 12 - Full closure between 9 a.m. and 1 p.m. Lane restrictions and flaggers, if needed, between 1 p.m. and 4:30 p.m.
Friday, Dec. 13 - Lane restrictions and flaggers between 6:30 a.m. and noon.

Motorists should also expect flaggers and possible delays between Superior and Top-of-the-World for a paving and guardrail project.

For more information, go to http://azdot.gov/PintoCreekBridge.

Drivers should proceed with caution, slow down and watch for construction personnel and equipment.   back...